Updated July 8, 2021 EAST BAY DIVISION FY22 CONSTRUCTION PROGRAM HIGHLIGHTS NON-RECURRING MAINTENANCE (NRM) PROJECTS REMODEL SPECIALTY CARE, BUILDING 19 PROJECT DESCRIPTION: The project
will upgrade and expand specialty clinical services by renovating existing space vacated by the Hematology/Oncology and Pharmacy services. PROJECT STATUS: Pre-solicitation phase CORRECT
MARTINEZ CAMPUS WATER SYSTEM PROJECT DESCRIPTION: The project will increase the current water pressure up to a minimum 75 psi across campus and provide an emergency water storage supply for
four days of potable water and fire protection. PROJECT STATUS: Awarded and in the 35% design phase Started: March 22, 2022 Planned completion date: Summer 2023 ADA DOOR CORRECTIONS FOR EAST
BAY PROJECT DESCRIPTION: The project is to correct deficiencies and accessibility of doors to include installation of automatic door openers PROJECT STATUS: Construction phase Started:
April 26, 2021 Planned completion date: Fall 2022 ELECTRONICS HEALTH RECORD MODERNIZATION, MARTINEZ PROJECT DESCRIPTION: The project includes to upgrade the IT Infrastructure throughout the
campus. All the existing Telecommunications rooms and data center to bring them up to the VA IT standards. This project included to upgrade data cables to CAT 6A and fiber upgrade to
OM4-rated multimode fiber-optic cable. PROJECT STATUS: Pre-award phase Planned start: August 2022 Planned completion date: June 2024 ELECTRONICS HEALTH RECORD MODERNIZATION, MARE ISLAND
PROJECT DESCRIPTION: The project includes to upgrade the IT Infrastructure throughout the campus. All the existing Telecommunications rooms and data center to bring them up to the VA IT
standards. This project included to upgrade data cables to CAT 6A and fiber upgrade to OM4-rated multimode fiber-optic cable. PROJECT STATUS: Design phase Start date: April 13, 2022 Planned
completion date: October 5, 2023 ELECTRONICS HEALTH RECORD MODERNIZATION, FAIRFIELD PROJECT DESCRIPTION: The project includes to upgrade the IT Infrastructure throughout the campus. All the
existing Telecommunications rooms and data center to bring them up to the VA IT standards. This project included to upgrade data cables to CAT 6A and fiber upgrade to OM4-rated multimode
fiber-optic cable. PROJECT STATUS: Design phase Start date: March 11, 2022 Planned completion date: September 2, 2023 MINOR PROJECTS CHRONIC DIALYSIS & SLEEP PROGRAM PROJECT
DESCRIPTION: The project is creating dialysis stations in the Center for Rehabilitation and Extended Care (CREC) including coffee shop, canteen expansion, and sleep study center. PROJECT
STATUS: Construction phase SLEEP STUDY CENTER Started: June 15, 2021 Planned completion date: April 25, 2023 COFFEE SHOP Started: February 7, 2022 Planned completion date: December 2, 2022
CANTEEN EXPANSION Planned Start: September 29, 2022 Planned completion date: June 1, 2023 CONSTRUCT PARKING STRUCTURE TO REPLACING EXPIRING LEASE PROJECT DESCRIPTION: The project would
look to create a parking structure to replace the leased parking area across Muir Rd. PROJECT STATUS: Project is in planning phase